204.

Apologies for Absence

Apologies for absence were received from Cllr Brown, Cllr Hollingsworth and Cllr Simm.

205.

Declarations of Interest

There were no declarations of interest.

206.

Public Questions

No public questions were received.

207.

Councillor Addresses on any item for decision on the Board's Agenda

Councillor Fooks addressed the Board on agenda item 9.  Her comments are included in the minutes for those items (212).

208.

Councillor Addresses on Neighbourhood Issues

There were no councillor addresses on neighbourhood issues.

209.

Scrutiny Committee Reports

No scrutiny committee reports were submitted to the meeting.

210.

Oxford and Abingdon Flood Alleviation Scheme pdf icon PDF 94 KB

The Executive Director Community Services has submitted a report which seeks authority to enter into an agreement with the Environment Agency in regard to funding the above scheme, and to seek project approval for the scheme.

 

Recommendations: That the City Executive Board resolves to:

 

1.    Authorise the Council’s entry into the proposed agreement with the Environment Agency, as described in this report, under which the Council would play an active role in the establishment of the business case of the Oxford and Abingdon flood alleviation scheme, and provide funding to a capped sum.

2.    Grant Project Approval for the Council’s involvement in the Oxford and Abingdon flood alleviation scheme, as described in this report.

Minutes:

The Executive Director Community Services submitted a report which sought authority to enter into an agreement with the Environment Agency in regard to funding the Oxford and Abingdon Flood Alleviation Scheme, and to seek project approval for the scheme.

 

The Executive Board Member, Corporate Strategy and Economic Development presented the report.  He confirmed that there was already budget provision; that the scheme was due to start in 2018, subject to further evaluation by the Treasury and DEFRA; and that it was hoped that the preferred route would be identified by June 2016 and that this would then be subject to public consultation.

 

The City Executive Board resolved to:

 

1.           Authorise the Council’s entry into the proposed agreement with the Environment Agency, as described in this report, under which the Council would play an active role in the establishment of the business case of the Oxford and Abingdon flood alleviation scheme, and provide funding to a capped sum.

 

2.                 Grant project approval for the Council’s involvement in the Oxford and Abingdon flood alleviation scheme, as described in this report.

211.

Bid for refurbishment and extension of car park for a public sector body pdf icon PDF 94 KB

The Executive Director Community Serviceshas submitted a report which seeks approval to enter into a contract for civil engineering works associated with the refurbishment and extension of a car park in Oxford for a public sector body.

 

Recommendations: That the City Executive Board resolves to:

1.    Authorise the entering into a contract for civil engineering work referred to in this report.

2.    To note that the contract will make a satisfactory contribution towards local overheads, as identified in the Not for Publication Annex attached.

Additional documents:

Minutes:

The Executive Director Community Services submitted a report which sought approval to enter into a contract for civil engineering works associated with the refurbishment and extension of a car park in Oxford for a public sector body.

 

The Executive Board Member, Finance, Corporate Asset Management and Public Health presented the report. The Board noted that this was a low risk project which drew on the Council’s skills and resources and that there was a market opportunity for the Council to continue to develop its service offering in this area.

 

The Board congratulated the Highways and Engineering Manager and his team on their success in winning bids and delivering external work to a high standard.

 

The City Executive Board resolved to:

 

1.       Authorise the entering into a contract for civil engineering work referred to in this report.

 

2.       Note that the contract will make a satisfactory contribution towards local overheads, as identified in the Not for Publication appendix.

212.

Devolution update pdf icon PDF 127 KB

The Assistant Chief Executive has submitted a report which updates the Board on devolution and seeks authorisation for further joint working in support of it.

 

Recommendations: That the City Executive Board resolves to:

 

1.    Agree to work with the other District Councils and partners to further develop the initial unitary devolution proposals.

2.    Agree that independent consultants should be jointly appointed by the Districts to undertake detailed work and a contribution of up to £50k be made to facilitate those studies.

3.    Recommend Council to allocate the budget of £50k to support the initial study on viability and sustainability and governance; specialist work on collaboration around Children and Adult services; public consultation and involvement; and preparation of a revised Devolution Deal. This will be funded from reserves and balances.

Minutes:

The Assistant Chief Executive submitted a report which updated the Board on the proposals for devolution and sought authorisation for further joint working in support of those proposals.

 

The Executive Board Member, Corporate Strategy and Economic Development and the Chief Executive presented the report.  The Board acknowledged that the overall objective of devolution was to stimulate the economy, deliver improved services and make savings for the benefit of the residents of Oxfordshire.

 

The Board noted that:

·         there were sufficient resources to meet the additional budget

·         that the details of the consultation process would be developed as part of this study by the external consultants, and that it would look at best practice models from other local authorities such as Dorset County Council

·         that initial feedback from Government indicated that the City and District Council proposals for devolution needed to be more ambitious and innovative in terms of governance (e.g. elected mayor and fewer tiers)

·         that the terms of reference for the study by the external included the requirement to look at a range of alternative models and options, including cross-boundary arrangements

·         that the proposals would be evaluated on the following criteria:

o   improved and sustainable strong leadership

o   value for money

o   improved service delivery

o   transition costs

o   savings

 

The City Executive Board resolved to:

 

1.    Agree to work with the other District Councils and partners to further develop the initial unitary devolution proposals.

2.    Agree that independent consultants should be jointly appointed by the Districts to undertake detailed work and a contribution of up to £50k be made to facilitate those studies.

3.    Recommend Council to allocate the budget of £50k to support the initial study on viability and sustainability and governance; specialist work on collaboration around Children and Adult services; public consultation and involvement; and preparation of a revised Devolution Deal. This will be funded from reserves and balances.

 

213.

Items raised by Board Members

No items were raised by Board Members.

Matters Exempt from Publication

The City Executive Board resolved to exclude the press and public from the meeting during consideration of the item in the exempt from publication part of the agenda in accordance with the provisions in Paragraph 21(1)(b) of the Local Authorities (Executive Arrangements) (England) Regulations 2000 on the grounds that their presence could involve the likely disclosure of exempt information as described in specific paragraphs of Schedule 12A of the Local Government Act 1972 and that, in all the circumstances of the case, the public interest in maintaining the exemption outweighed the public interest in disclosing the information.

214.

Confidential Appendix: Bid for refurbishment and extension of car park for a public sector body

This is exempt from publication by virtue of Paragraph 3, Part 1 of Schedule 12A of the Local Government Act 1972 for the following reasons:

 

           Commercial affairs of the Council.

Minutes:

The Board received and noted the contents of the not for publication appendix to the report on the bid for refurbishment and extension of a car park for a public sector body (agenda item 8; minute 211).