Issue history

Issue history

Appointment of Baily Garner LLP to support the delivery of the Youth Hub project at The Leys Pools & Leisure Centre

Published Related issues
TitleDate CreatedDue DateDecision MakersIssue Status
The Leys Pool and Leisure Centre - Youth Hub06/07/2023Before 31 Dec 2025Cabinet, Council, Executive Director (Communities and People)For Determination
Pre-construction Services Agreement (PCSA) with Oxford Direct Services (ODS) for the youth hub at the Leys Pools & Leisure Centre13/05/20248 May 2024Executive Director (Development)Recommendations Approved
Decision to enter into a Letter of Intent (LOI) with Oxford Direct Services (ODS) to undertake works necessary to be in a position to enter into a construction contract to create a youth hub based in the Leys Pools & Leisure Centre02/08/20242 Aug 2024Executive Director (Communities and People)Recommendations Approved