Issue history
Collaboration agreement with the Council’s bid partners for the implementation of an Electric Vehicle Strategy with Associated Infrastructure.
Title | Date Created | Due Date | Decision Makers | Issue Status |
---|---|---|---|---|
Implementation of an Electric Vehicle Strategy with Associated Infrastructure to support Targeted Improvement of Air Quality. | 08/03/2019 | Officer Executive Decisions, , Head of Corporate Strategy, Head of Corporate Property | Recommendations Approved | |
Award of contract to Gamma Energy for Energy Superhub Oxford DC Charging | 18/11/2021 | 16 Dec 2021 | Head of Corporate Strategy | Recommendations Approved |
Lease agreement with Pivoted Power LLP for the substation at Redbridge Park and Ride. | 18/11/2021 | 16 Dec 2021 | Head of Corporate Property | Recommendations Approved |
Award of contract to Tesla for Energy Superhub Oxford DC Charging | 18/11/2021 | 16 Dec 2021 | Head of Corporate Strategy | Recommendations Approved |
Award of contract to Gamma Energy for Energy Superhub Oxford DC Charging | 11/04/2022 | 8 Apr 2022 | Head of Corporate Strategy | Recommendations Approved |
Contract for the installation of high voltage cables at the Oxford Energy Superhub | 03/05/2022 | 25 Apr 2022 | Head of Corporate Strategy | Recommendations Approved |
Award of contract to Kek Tech Ltd for the Energy Superhub Oxford data evaluation project | 03/05/2022 | 6 Apr 2022 | Head of Corporate Strategy | Recommendations Approved |
Award of contract to Witney Cables for low voltage works at Energy Superhub Oxford | 03/05/2022 | 6 Apr 2022 | Head of Corporate Strategy | Recommendations Approved |