Issue details

Issue details

Blackbird Leys Development Project - Compulsory Purchase Order

To seek delegated authority for the Executive Director (Development) to make a Compulsory Purchase Order to support the obtaining of vacant possession of properties required to complete Phase 2 of the Blackbird Leys Development Project.

Decision type: Non-key

Decision status: For Determination

Wards affected: Blackbird Leys;

Notice of proposed decision first published: 01/07/2024

Decision due: 11 Sep 2024 by Cabinet

Lead member: Cabinet Member for Housing and Communities, Deputy Leader (Statutory) - Finance and Asset Management

Lead director: Executive Director (Development), Head of Corporate Property

Department: Corporate Property dept

Contact: Bruce McRobie, Capital Programme Surveyor Email: bmcrobie@oxford.gov.uk.

Reason date could change: Confirmed for this meeting

Is the date subject to change: Yes