Contract for Rebuild Cost Assessments
Cabinet, on 12 June 2024, resolved to:
1. Recommend to Council the provision of a revenue budget in the General Fund for the sum of £128,000 per annum for the next three years and in the HRA for the sum of £55,000 per annum; and
2. Delegate authority to the Head of Corporate Property, in consultation with the Head of Law and Governance; the Head of Financial Services; and the Deputy Leader (Statutory) – Finance and Asset Management to agree the cost and final terms of, and enter and make any necessary amendments to, a contract with the preferred supplier.
Decision type: Key
Reason Key: Expenditure, income or savings of £500,000 or greater;
Decision status: For Determination
Notice of proposed decision first published: 01/05/2024
Decision due: 12 Jun 2024 by Cabinet, Council
Decision due: Before 31 Dec 2025 by Head of Corporate Property
Considered on: 16 May 2024 by Council
Lead member: Deputy Leader (Statutory) - Finance and Asset Management
Lead director:
Department: Corporate Property dept
Contact: Ted Bowler, Corporate Asset Manager Email: tbowler@oxford.gov.uk.
Reason date could change: Confirmed for this meeting