East Oxford Community Centre - project inflation and award of construction contract

To approve a virement of up to £900k from the Council’s construction inflation budget to meet the current projected overspend on the East Oxford Community Centre budget, which is as a result of construction inflation of around 19% which has impacted the project since the budget was last approved. To subsequently approve the award of the construction contract to ODS.

Decision type: Key

Reason Key: Expenditure, income or savings of £500,000 or greater;

Decision status: Abandoned

Notice of proposed decision first published: 20/03/2023

Anticipated restriction: Part exempt  -

Decision due: Not before 28 Mar 2023 by Chief Executive

Lead member: Cabinet Member for Inclusive Communities and Culture

Lead director: Executive Director (Communities and People)

Department: Community Services

Contact: Hagan Lewisman, Active Communities Manager Email: hlewisman@oxford.gov.uk Tel: 01865 252706.