1-3 George Street comprises a vacant mixed use building in a prime city-centre location. The building’s condition has deteriorated internally and in its current condition does not meet minimum regulatory energy performance and other standards. It now requires significant works to refurbish the building to provide a rental income to the council.

The project will deliver an increased level of refurbishment and will improve the attractiveness of the building to the market. Works are to include a new external lift servicing all floors, internal layout improvements to support flexible working, enhanced services, and fabric improvements to improve energy efficiency, a rear external terrace and internal lightwell.

The proposal aims to secure a BREEAM Very Good, sustainability standard through further improvements to the building fabric, both air-tightness and insulation, enhancement to triple glazed windows, as well as the use of PV at roof level.

Decision type: Key

Reason Key: Expenditure, income or savings of £500,000 or greater;

Decision status: Recommendations Approved (subject to call-in)

Notice of proposed decision first published: 04/09/2020

Decision due: 20 Jan 2021 by Cabinet

Decision due: 25 Jan 2021 by Council

Decision due: Before 31 Dec 2021 by Executive Director (Development)

Lead member: Cabinet Member for Planning

Lead director: Executive Director (Development)

Contact: Andrew Humpherson, Regeneration Manager Email: Ahumpherson@oxford.gov.uk.

Decisions