Infrastructure Place Study - Cowley Branch Line
22/12/2023 - Infrastructure Place Study - Cowley Branch Line
SLC Rail have been appointed using the Bloom
Procurement Services Ltd framework to undertake Infrastructure
Place Study work.
Contract value for this commission is £498,799.
This will support the successful strategy and implementation plan
for a regionally significant transport scheme. It will enable
Oxford City Council and other local parties to ensure the rail
scheme contributes to the creation and improvement of the
neighbourhoods around the proposed two new stations.
The CBL budget is £4,560,000.
• Committed spend for the delivery of the Full Business Case
and project Management (including legal support) is
£3,603,095.
• Committed spend for the delivery of feasibility and design
work cycle and footbridge near the proposed Oxford Cowley Station
is £133,484
• Remaining budget after this decision is £326,572.