Agenda item
East West Rail Phase 1 - rail damping route sections H (16/01858/VAR) and I-1 (16/01861/VAR)
- Meeting of West Area Planning Committee, Tuesday 13 September 2016 6.00 pm (Item 46.)
- View the background to item 46.
Note re appendices
· Appendix 1 is common to agenda items 3 and 4 (found on page 35)
· Appendices 2 and 3 are common to agenda items 3, 4 and 5 (pages 37 and 39)
· Appendix 4 and 5 a, b, c are specific to this report (pages 53, 63 - 77)
Minutes:
Discussion
The Committee considered two applications for the removal of conditions in relation to the use of ‘Tata SilentTrack’ in route sections H and I-1.
The Planning Officer presented the report. In summary she explained that that planning officers’ were not saying that the use of ‘Tata SilentTrack’ was reasonably practicable but that the applicant had not submitted a convincing case that the use of ‘Tata SilentTrack’ was not reasonably practicable for use on route sections H and I-1.
The following residents spoke against the application: Mr Mike Gotch, Mr Keith Dancey, Mr Paul Buckley, Mr Adrian Olsen.
Representatives from Network Rail gave a presentation in support of the application.
The Committee asked questions of the officers and Network Rail representatives about the details of the applications.
In reaching their decisions, the Committee considered the officers report and presentation, the address of the public speakers and the presentation by Network Rail.
The Committee concluded that the applicant had not demonstrated to the Council’s overall satisfaction that the use of ‘Tata SilentTrack’ was not reasonably practicable for use on route sections H and I-1.
Decisions
Supporting documents:
- EWRP1 - rail damping route sections H and I-1 (2 applications) - Final, item 46. PDF 224 KB
- Appendix 1 site map - for SilentTrack and monitoring reports, item 46. PDF 54 KB
- Appendix 2 for all reports - Condition 19, item 46. PDF 76 KB
- Appendix 3 for all reports - Noise and vibration mitigation policy CD1.29 2.1, item 46. PDF 181 KB
- Appendix 4 - ARUP report for SilentTrack report only, item 46. PDF 1 MB
- Appendix 5 - for SilentTrack report only, item 46. PDF 70 KB View as DOCX (46./6) 15 KB
- Appendix 5a - Unipart Rail Infrastructure Catalogue - for SilentTrack report only, item 46. PDF 2 MB
- Appendix 5b - Rail dampers performance - for SilentTrack report only, item 46. PDF 1 MB
- Appendix 5c - photo - for SilentTrack report only, item 46. PDF 520 KB View as DOCX (46./9) 524 KB
- WAPC presentation for East West Rail Phase 1 applications - 13.09.2016 v2, item 46. PDF 177 KB
- Note submitted by EWR - re points made at WAPC Briefing 07 09 16, item 46. PDF 71 KB
- Network Rail presentation to WAPC 13 September (v2), item 46. PDF 1 MB