Decision details
Application of Feed-In Tariff to Council Buildings
Decision Maker: City Executive Board (became Cabinet on 13 May 2019)
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Purpose:
Report concerning the application of a feed-in tariff to Council buildings in respect of surplus energy production.
Decisions:
The Head of Environmental Development submitted a report (previously circulated, now appended) seeking approval to proceed with the pilot of a scheme to realise the benefits of the feed-in tariff.
Resolved to:-
(1) Grant project approval for installation of photovoltaics on the buildings set out in the report;
(2) Make available £670,000 of capital expenditure to fund the project and include in the General Fund and Housing Revenue Account capital programmes subject to sufficient shortfall being identified in the Quarter 3 monitoring report;
(3) Authorise the Executive Director for City Services to undertake the project subject to the payback period not exceeding 15 years.
Report author: Jenny Davidson
Publication date: 08/12/2011
Date of decision: 07/12/2011
Decided at meeting: 07/12/2011 - City Executive Board (became Cabinet on 13 May 2019)
Effective from: 15/12/2011