Decision details

Decision details

Tumbling Bay

Decision Maker: Head of Corporate Property

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Purpose:

The decision outlines options for restoring the asset to a good state of repair. Options to include replacing, renovating, or removing.

Decision:

The decision to proceed with this options appraisal was made to ensure a responsible allocation of funds for Tumbling Bay Bridge. The consultant’s report will provide information, including high-level drawings, material options, costs, and a phased methodology for potential removal or construction. This £9,736.90 expenditure is a strategic investment to guide future planning, reduce long-term costs, and mitigate project risks by evaluating options for this bridge.

Reasons for the decision:

As the responsible authority for this bridge, Oxford City Council has to make sure that it is safe and serviceable.

Alternative options considered:

The review carried out by the appointed consultant will consider all options available to us and which option would be best value for Oxford City Council.

Publication date: 19/11/2024

Date of decision: 07/10/2024

Accompanying Documents: