Decision details

Decision details

Trill Mill Bridge Options Appraisal

Decision Maker: Head of Corporate Property

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Purpose:

The decision will allow for options to be gathered for restoring the asset to an appropriate state of repair. Options to include replacing, renovating, or removing.

Decision:

The decision to proceed with this options appraisal was made to ensure responsible allocation of funds for Trill Mill Bridge. The consultant’s report will provide information, including high-level drawings, material options, costs, and a phased methodology for potential removal or construction. This £9,736.90 expenditure is a strategic investment to guide future planning, reduce long-term costs, and mitigate project risks by evaluating options for this bridge.

Reasons for the decision:

As the responsible authority for this bridge, Oxford City Council is responsible to see that the asset is fit for public use.

Alternative options considered:

The review carried out by the appointed consultant will consider all options available to us and which option would be best value for Oxford City Council. There is no other present option.

Publication date: 19/11/2024

Date of decision: 07/10/2024