Appointment of Baily Garner LLP to provide services to support the delivery of the Youth Hub project at The Leys Pool & Leisure Centre
Decision Maker: Head of Community Services
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Purpose:
This decision is delegated to officers under Part 4.4 of the Council’s Constitution: All executive functions except those in Part 4.5, 4.6 and 4.7 are delegated to the officers in the senior management structure.
Decision:
To appoint Baily Garner LLP to carry out Project Manager, Principal Designer, Employer’s Agent/Contract Administrator and Quantity Surveyor services as a direct award under the Fusion 21 Consultancy Framework to support the delivery of the Youth Hub project at the Leys Pools and Leisure Centre.
Reasons for the decision:
The decision enables the Council to enter into a Deed of Appointment with Baily Garner LLP (through the Fusion 21 Framework) to provide Project Manager, Principal Designer, Employer’s Agent/Contract Administrator and Quantity Surveyor services. It is essential to ensure that the services performed by the appointed contractor are properly administered and that the pre-construction/ construction phase is planned, delivered and monitored in a safe and efficient manner. The Council cannot deliver these services in-house.
Alternative options considered:
A mini competition under the framework was considered. However due to constraints to the project, the decision was made to direct award under Part 19.12 of the Constitution. Direct award is a permissible option under the Fusion 21 Framework. The option not to procure the appointment was rejected as the Council cannot deliver the required services in-house.
Signed off by senior officers:
Decision taken by Ian Brooke, Head of Community Services.
Publication date: 31/01/2024
Date of decision: 31/01/2024