Port Meadow mooring infrastructure - feasibility study.

Decision Maker: Executive Director (Development)

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Purpose:

To provide specialist advice to inform future options for the Port Meadow moorings .

 

Decision:

The decision is to appoint consultants to provide specialist advice through the undertaking of a feasibility study to help inform future options for the moorings.

Following a tendering exercise, a preferred supplier has been chosen – Rothen Group, which is an expert in delivering waterways engineering and marina construction. 

 

Alternative options considered:

An internal review is not an option as officers do not have the required skill sets.

 

Signed off by senior officers:

Tom Bridgman, Executive Director for Development.

Decision taken in consultation with the Cabinet Member for Finance and Asset Management.

Publication date: 21/08/2020

Date of decision: 20/07/2020