Purpose:

Report concerning the application of a feed-in tariff to Council buildings in respect of surplus energy production. 

Decisions:

The Head of Environmental Development submitted a report (previously circulated, now appended) seeking approval to proceed with the pilot of a scheme to realise the benefits of the feed-in tariff.

                                                                                                           

Resolved to:-

 

(1)   Grant project approval for installation of photovoltaics on the buildings set out in the report;

 

(2)   Make available £670,000 of capital expenditure to fund the project and include in the General Fund and Housing Revenue Account capital programmes subject to sufficient shortfall being identified in the Quarter 3 monitoring report;

 

(3)   Authorise the Executive Director for City Services to undertake the project subject to the payback period not exceeding 15 years.

Report author: Jenny Davidson

Publication date: 08/12/2011

Date of decision: 07/12/2011

Decided at meeting: 07/12/2011 - City Executive Board (became Cabinet on 13 May 2019)

Effective from: 15/12/2011

Accompanying Documents: