19/11/2021 - Heat Decarbonisation Plan for Three Buildings ref: 2242    Recommendations Approved

Oxford City Council declared a climate emergency in 2019 and organised a Citizen’s Assembly on Climate Change. The City Council has since committed to achieve net zero emissions across its estate and operations by 2030.

The 4th Carbon Management Plan (CMP) sets out the steps the Council will take to achieve this 2030 target, which equates to an approximate doubling of previous rates of carbon reduction, from 5% to 10% per year.

The CMP identified the need for the Council to produce a Heat Decarbonisation Plan (HDP) for large emitting sites. The purpose of a HDP is to provide a clear roadmap to decarbonisation as well as fully costed, detailed assessments for future funding and budget bids.

Decision Maker: Head of Corporate Property

Decision published: 13/12/2021

Effective from: 19/11/2021

Decision:

To award of a contract to Faithful & Gould to provide Heat Decarbonisation Plans for the Town Hall, St Aldates Chambers and Barton Neighbourhood Centre, to be completed by 31st March 2022.


19/11/2021 - 50 - 72 Masons Road, Wood Farm, Oxford OX3 8QW ref: 2234    Recommendations Approved

This block of flats has been experiencing structural movement for some years.  The cause of the movement has not been fully determined, although several hypotheses have been suggested.

The cause needs to be definitively determined, then stabilisation works and repairs executed.

Several of the residents have expressed concern about the cracks.  Tenants have been moved out of two of the flats due, indirectly, to the damage.  Others have asked for alternative accommodation, due to their perception of a risk.

Decision Maker: Head of Housing Services

Decision published: 24/11/2021

Effective from: 19/11/2021

Decision:

 

Award of contract to Wilde Consulting Engineers to undertake work at 50 - 72 Masons Road, Wood Farm, Oxford OX3 8QW  for the value of c £80k in accordance with Part 19.11 of the Constitution

The cost of the necessary engineering services will be in the region of £80k including a 15% contingency.

A quotation has been provided by Wilde Consulting Engineers, via the South East Business Portal.

 

 


16/11/2021 - Award of contract to Tesla for Energy Superhub Oxford DC Charging ref: 2233    Recommendations Approved

Supply and installation and operation and maintenance of 12 DC charge points at Redbridge Park and Ride under a concession contract.

Decision Maker: Head of Corporate Strategy

Decision published: 18/11/2021

Effective from: 16/11/2021

Decision:

To award a contract to Tesla for the provision of 12 DC charge points at Redbridge Park and Ride at zero cost to the Council for a contract period of 15 years with an option to extend for a further 5 years.


05/11/2021 - Lease & Licence for Alterations for a substation at Redbridge Park and Ride. Easement to enable cable to be laid for a further substation near Watlington Road with Pivoted Power LLP ref: 2232    Recommendations Approved

The substation will allow a termination point for the private wire delivering electricity for the EV hub at Redbridge and the cable easement will provide future electrification projects near Watlington Rd.

Decision Maker: Head of Corporate Property

Decision published: 18/11/2021

Effective from: 05/11/2021

Decision:

To grant a licence for alterations with Pivoted Power LLP for the substation at Redbridge Park and Ride to be built and a 30 year lease for the land. Grant a deed of easement for an electricity cable relating to Land off WatlingtonRoad, Oxford.


16/11/2021 - Award of contract to Gamma Energy for Energy Superhub Oxford DC Charging ref: 2231    Recommendations Approved

Supply and installation and operation and maintenance of a minimum of 10 x Charging Bays at Seacourt Park and Ride, under a Concession Contract.

Decision Maker: Head of Corporate Strategy

Decision published: 18/11/2021

Effective from: 16/11/2021

Decision:

To award a contract to Gamma Energy for the provision of a minimum of 10 charging bays at Seacourt Park and Ride at zero cost to the Council for a contract period of 10 years.